PA19/02040 | EIA screening request for highway improvements to Loggans Moor roundabout - Hayle A30 Loggans Moor Roundabout

EIA screening request for highway improvements to Loggans Moor roundabout - Hayle A30 Loggans Moor Roundabout

Ref. No: PA19/02040 | Received date: Wed 06 Mar 2019 | Status: Pending Consideration | Case Type: Planning Application

"Existing planning permissions for adjacent developments (PA14/02920 and PA16/04643) required an upgrade to this junction before development can begin"

PA14/02920 Walker Rugby

Rugby Club Development - Walker Developments PA14 02920

Outline application with some matters reserved for proposed development of up to 15,539 sq.m. (gross) retail development (A1/A3), associated infrastructure, access arrangements, servicing, parking and landscaping.

Hayle Rugby Club 10 Marsh Lane Hayle Cornwall TR27 5HX
Ref. No: PA14/02920 |Validated: Mon 31 Mar 2014 |Status: Decided]

PA16/04643 / PA16/03519 Cranford

Cranford Developments - Marsh Lane

EIA screening opinion in respect of application PA16/03519 for erection of retail development (Class A1), including all associated access, servicing and infrastructure works, car parking, public realm improvements and landscaping together with enhancement works including footpaths, bird hide and landscaping to the nature reserve and surrounding land

Land Between Loggans Moor Roundabout And Marsh Lane Industrial Estate Marsh Lane Hayle Cornwall
Ref. No: PA16/04643 | Validated: Thu 19 May 2016 | Status: Decided

Erection of retail development (Class A1), including all associated access, servicing and infrastructure works, car parking, public realm improvements and landscaping together with enhancement works including footpaths, bird hide and landscaping to the nature reserve and surrounding land.

Hayle Retail Park And Marsh Lane Nature Reserve Marsh Lane Hayle Cornwall
Ref. No: PA16/03519 | Validated: Fri 29 Apr 2016 | Status: Decided]


 


Date Published Document Type Measure Drawing Number Description View
  08 Mar 2019 Application Documents Cannot Measure Document  IMPORTANT INFORMATION, PLEASE READ View Document
  06 Mar 2019 Application Documents Cannot Measure Document  SCREENING REQUEST View Document
  06 Mar 2019 Plan - Proposed Measure Document EDG1459-1CSL-HGN-SW575385 OPTION 3D View Document

Hayle A30 Junctions-— Screening request for improvements to the A30 (T)

Loggans Moor Roundabout

Further to the response from Cornwall Council to a ‘Do I Need Planning permission’
request for Loggans Moor roundabout, Hayle (reference PA19/00417/PREAPP) I am
writing to formally request a screening opinion for the same scheme under regulation 5
of the Town and Country Planning (Environmental Impact Assessment) Regulations 1999
(as amended).

Highway improvements to Loggans Moor roundabout are proposed in order to increase
the vehicular capacity of the junction to cope with future traffic demand, as a result of
development highlighted in the Local Plan.

Existing planning permissions for adjacent developments (PA14/02920 and PA16/04643)
required an upgrade to this junction before development can begin. The initial design for
the roundabout, included as part of the Planning Applications is no longer supported by
Highways England. An alternative layout has been produced in working partnership
between Cornwall Council and Highways England, which has sufficient capacity to cope
with predicted traffic increases to the year 2030.

Cornwall Council are proposing to deliver the junction improvement at Loggans Moor
roundabout and are currently seeking external funding to meet the costs for delivery.
This will enable previously approved and future development in the Hayle and wider area
to proceed without the financial burden of improving the junction at the same time. Third
party land that is required to construct the scheme is currently under negotiations for
purchase between Cornwall Council and the landowner, for use as public highway

The proposed layout of the roundabout, which has been produced in a working
partnership with Highways England can be seen on drawing EDG1459-1-CSL-HGN-
SW575385-DE-D-0004 and comprises:

  • The installation of traffic signals onto the roundabout and A30 approaches, with
    associated ducting, traffic signal poles / heads and CCTV system.
  • Widening the A30 westbound entry into the roundabout to two additional lanes
    extending easterly into adjacent private land.
  • Widening the Marsh Lane entry onto the roundabout to provide an additional lane,
    extending westerly within the current hiqhway boundary and easterly into adjacent
    private land (County Wildlife Site).
  • Widening the A30 eastbound entry/westbound exit to create three additional lanes,
    extending easterly and westerly within the current highway boundary.
  • Widening the Carwin Rise (Hayle) entry into the roundabout to provide a bypass
    lane within the current highway boundary.
  • Provision of four lanes through the centre of the existing roundabout (two A30
    lanes, each direction).
  • Resurfacing existing roundabout carriageways and footways.
  • Provision of new footway between Carwin Rise (Hayle) and A30 eastbound entry
    including widening into adjacent private land.
  • Amendments to existing and provision of new drainage.
  • Provision of attenuation pond in private land.
  • Extending existing culverts.
  • Removal/amendments to existing vehicle restraint systems and provision of new.
  • Vegetation clearance and tree removal.
  • Retaining wall or strengthened earth embankment to retain the existing
    embankment between A30 Loggans Moor roundabout and the land to the north,
    within the current highway boundary.
  • Possible diversion of existing watercourses.
  • Removal of the existing pedestrian bridge.

Loggans Moor roundabout is located to the north-east of Hayle on the A30 (OS grid
reference SW 575,385). The roundabout lies approximately 250m south of into a notified
Site of Special Scientific Interest (SSSI), immediately next to a Cornwall Wildlife Site and
the biological roadside verge inventory indicates the presence of Lutra Lutra (Otters) and
what is described as interesting wetland flora.

The development site in terms of permanent and temporary working areas covers 4ha.
The likely environmental impacts comprise:

  • Temporary disturbance to watercourses.
  • Temporary disturbance to biological roadside verge inventory.
  • Temporary siltation of water bodies/watercourses.
  • Temporary traffic impact to the local hiqhway network with construction traffic
    using the network to access the site and manoeuvre materials.

Hayle has approximately 1600 new homes and nearly 40,000sqm of new employment
space allocated through the framework plan to 2030. The project’s main aim is to provide
a capacity upgrade to Loggans Moor roundabout to support the growth and manage
predicted congestion and safety concerns.
It is currently proposed to start construction in 2021/2022.

Please do not hesitate to contact me should you wish to discuss further.
Yours faithfully

David Phillips

Project Manager (Strategic Projects)

Engineering Design Group

 

 

Book page

TitleCreated
240325 | Open letter to all party candidates | sign to help Cornwall Wildlife Trust make difference for Nature at election 20 hours 53 min agoBook page
240310 | Detailed plans for affordable-led housing in Connor Downs 10th March 2 weeks 3 days agoBook page
240310 | Waste collections changes Helston, Penzance, Hayle | second phase:food waste, recycling, rubbish - commences July 2 weeks 3 days agoBook page
240218 | Collapsed North Quay development in Hayle described as a 'sea of despair' 5 weeks 15 hours agoBook page
240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats 5 weeks 3 days agoBook page
240220 | Poling works | Grist Lane and Marsh Lane, Angarrack | expected 20 Feb 2024 0830-1630, for one day 7 weeks 1 day agoBook page
231130 | Are you ready for weekly food waste recycling? | Food Waste, Recycling and Rubbish Collection Changes 16 weeks 2 hours agoBook page
230821 | People of Cornwall town 'thrown under bus' over housing plan | direct result of councillors handled Hayle masterplan 31 weeks 1 day agoBook page
230817 | When will new rubbish collection changes start, Cornwall 31 weeks 6 days agoBook page
230809 | Holiday park in Cornwall for emergency housing still empty | Sandbank site purchased Cornwall Council in Jan 2022 32 weeks 5 days agoBook page
230811 | Decision on huge solar farm at Carnhell Green: refused 32 weeks 5 days agoBook page
230809 | Nearest NHS dental practice to Cornwall taking new patients 32 weeks 5 days agoBook page